Research factsheet28 September 2026
Download PDF
ROCKAIMXRockfire Resources PLC
Interim Results · RNS 5315W · 28 September 2026

Rockfire's interim loss nearly doubles as Molaoi resource upgrade slips into 2027

Share price0.14p
Market cap£14.7m
52-week range0.1p – 0.25p
Shares in issue10665.0m
12-month change-34.5%
Ticker Data API, as at 27 Nov 2026, 16:26

Share price, 12 months

0.1p0.15p0.2p0.25p Announcement, 28 September 2026Dec 25Feb 26Apr 26Jun 26Aug 26Oct 26

Summary

Rockfire's interim results today showed a total comprehensive loss of £1,126,157 for the six months to 30 June 2026, up from £627,224 a year earlier, as drilling and project work at its Molaoi zinc-germanium deposit in Greece picked up. Cash stood at £1,829,762 at 30 June, helped by £3,131,250 of share issues, and a further £2.15m was raised at 0.11p in August. The company says the long-promised upgrade of Molaoi from Inferred to Indicated resource is taking longer than expected, blaming broken ground and a shortage of rigs and drillers. Drilling will continue until at least the end of 2026, with a pre-feasibility study due to start in the second quarter of 2027. The committee sees encouraging drill results but is concerned about repeated discounted fundraisings, a share price near its nominal value and slipping timetables.

Key figures

FigureValuePeriodChange
Total comprehensive loss£1,126,1576 months to 30 June 2026Up £498,933 from £627,224
Loss before taxation£1,289,5666 months to 30 June 2026From £536,087
Cash and cash equivalents£1,829,76230 June 2026From £1,057,236 at 31 December 2025
Net cash outflow from operating activities£1,215,8616 months to 30 June 2026From £547,914
Exploration expenditure (capitalised)£860,8406 months to 30 June 2026From £195,632
Proceeds from issuance of ordinary shares£3,131,2506 months to 30 June 2026
Post-period subscription£2.15 million at 0.11 penceAnnounced 10 August 2026
Warrants outstanding at 0.1p688,750,00030 June 2026
Ordinary shares in issue10,665,020,71728 August 2026
Sources: Interim Results RNS, 28 Sep 2026; Total Voting Rights RNS, 28 Aug 2026

The announcement

Against guidance

In September 2025 the company said drilling planned for the second half of 2025 was expected to lift the Molaoi resource from Inferred to Indicated, and that the next phase of drilling would also aim to establish a maiden JORC resource for germanium. Today's results say the Indicated upgrade remains in progress, with drilling expected to continue until at least the end of 2026 and a pre-feasibility study scheduled to start in Q2 2027. No maiden germanium resource is reported. The company's own rig, committed to in April 2026, has also slipped: recent updates moved its expected arrival from late September/early October to 18 November 2026.

Bull case

  • Drilling continues to return potentially economic grades of zinc, silver and germanium, including 11.90m @ 8.8% Zn and 25.2g/t Ge in HMO-015. Germanium is a strategically relevant metal for Europe.
  • An engineering appraisal found the historical underground workings at Molaoi in good condition and likely reusable. Early comminution and rock-strength tests have also been encouraging.
  • Cash rose to £1,829,762 at 30 June and a further £2.15m was raised in August. Partners fund the Australian projects: Eastern Resources is sole-funding Marengo exploration for three years, giving non-dilutive optionality.

Bear case

  • Rockfire has no revenue and depends on repeated equity raises at discounts; the August subscription was priced at an 18% discount. The share price sits close to the 0.1p nominal value, leaving little room for further discounted placings without a capital reorganisation.
  • Key milestones have slipped. The Indicated upgrade guided for H2 2025 is still in progress, no germanium resource has been published, and the rig delivery date has moved repeatedly.
  • Losses and cash spending more than doubled year on year, and 400m options were granted to management shortly after the 0.11p placing. The committee also flagged thin trading liquidity and a difficult UK interest-rate backdrop for speculative explorers.
  • Any eventual mine development would require capital far beyond the size of an £11m company, implying further dilution.

What to watch

This research is produced by Ticker using automated analysis of company announcements, filings and market data. It is for information only, is not personal advice or a recommendation to buy or sell any security, and may contain errors. Past performance is not a reliable indicator of future results. The value of investments can fall as well as rise. Market data from Ticker's Data API as at 27 Nov 2026, 16:26.