Summary

Block Energy's interim results today showed a company making commercial progress while its producing base weakens. In the six months to 30 June 2026 it completed the Aspect XIQ farm-out, signed a binding Framework Agreement with Sanning for Project III and entered offshore Gabon. Production, however, fell to 374 boepd from 483 boepd, revenue slipped to US$2.887 million and operating cash flow turned to a US$415,000 outflow. Cash of US$2.690 million came from a share placing at 1.1p, not from the business. The directors retain a material uncertainty over going concern, and a US$2.0 million secured loan falls due in August 2027.

Key figures

FigureValuePeriodChange
Average daily production374 boepdH1 2026From 483 boepd in H1 2025
RevenueUS$2.887 millionH1 2026From US$3.380 million in H1 2025
Weighted average realised oil priceUS$80.6/bblH1 2026From US$60.5/bbl in H1 2025
Adjusted EBITDA (group)US$56,000H1 2026From US$81,000 in H1 2025
Net cash from operating activities-US$415,000H1 2026From US$171,000 generated in H1 2025
Cash and cash equivalentsUS$2.690 million30 June 2026From US$1.493 million at 31 December 2025
Advances to Pilgrim (convertible loan note)US$4.312 million30 June 2026US$1.688 million undrawn of a US$6.0 million facility
Secured loanUS$2.0 millionDue August 2027
Ordinary shares in issue1,469,379,95530 June 2026From 1,011,647,492 at 31 December 2025
Share price0.82pBelow the 1.1p placing price
Sources: Interim Results RNS, 28 Sep 2026; Interim Results RNS, 28 Sep 2026 (note 9); Interim Results RNS, 28 Sep 2026 (note 8); Ticker market data

The announcement

Against guidance

The full-year results on 1 June 2026 targeted definitive Sanning documentation for the second half of 2026, with operations in the first half of 2027; today's update says the documents are well advanced but unsigned, and keeps H1 2027 for appraisal, subject to completion and approvals. The Aspect seismic, which the June operations update said would start in July and run about three months, is now expected to complete acquisition by mid-October. On the producing side, the 1H 2025 interim had described production as stable; this half it fell materially.

Bull case

  • Block has shown it can land partners: the Aspect farm-out completed and the carried seismic is visibly under way, while Sanning is a binding framework offering up to US$75 million of carry on 2.77 Tcf of gross 2C gas.
  • Several potential 2027 catalysts are lined up—seismic interpretation and drilling decisions at Martkopi, Project III appraisal, and preliminary partner talks on Gabon's four historical discoveries.
  • The share price, below the 1.1p placing price, gives little credit to Sanning, Gabon or higher oil, so a signed and approved Sanning deal or a Gabon partner that recycles Block's advances could exceed subdued expectations.
  • Higher oil prices, with Brent at 108 $/bbl against H1's US$80.6/bbl realised, could lift second-half receipts if well interventions stem the production decline.

Bear case

  • The producing business is not funding the group: Georgian adjusted EBITDA of US$794,000 was almost entirely absorbed by US$738,000 of corporate costs, and operating cash flow was negative. Partner carries pay for seismic and drilling, not head-office costs.
  • The US$2.0 million loan falls due in August 2027, the directors retain a material going-concern uncertainty, and cash came from a placing that lifted the share count sharply—pointing to likely further dilution before any value-crystallising event.
  • Gabon is currently a US$4.312 million loan receivable with no PSC interest or control until conversion, with a further US$1.688 million available to draw and up to US$4.0 million of non-cash support committed.
  • Timetables are already stretching: Sanning's definitive documents were targeted for H2 2026 and remain unsigned; resources quoted are unrisked prospective and contingent estimates, not reserves.

What to watch

This research is produced by Ticker using automated analysis of company announcements, filings and market data. It is for information only, is not personal advice or a recommendation to buy or sell any security, and may contain errors. Past performance is not a reliable indicator of future results. The value of investments can fall as well as rise. Market data from Ticker's Data API as at 23 Nov 2026, 08:51.